PHOTOS: TRON Lightcycle Run Supports Repositioned to Install Higher Section of Canopy at the Magic Kingdom

Iain

20210220-dsc04503

PHOTOS: TRON Lightcycle Run Supports Repositioned to Install Higher Section of Canopy at the Magic Kingdom

It was a week ago when we noticed that temporary support structures were beginning to be dismantled from TRON Lightcycle / Run, the latest attraction to come to the Magic Kingdom. Today, we saw that even more temporary supports have been removed from parts of the canopy while some have been added to support the installation of higher parts of the canopy.

20210220-dsc04477
20210220-dsc04476

The latest temporary supports have been added to prepare for the installation of the canopy at the higher sections of the structure.

20210220-dsc04478
20210220-dsc04479

From this angle, we can see that the canopy has taken a nice curved shape.

20210220-dsc04500

Though there is no activity at the moment, heavy machinery remain on-site as construction hauls on.

20210220-dsc04499

Here, the pinnacle of the canopy is noticeable as the temporary supports have formed a very high peak.

20210220-dsc04501

These brown structures are the temporary supports, holding up the integrity of the canopy.

20210220-dsc04502

Some roof work of the show building is visible as well.

20210220-dsc04503
20210220-dsc04505

The peak is just about as tall as the building. The next step for the canopy work will be for more steel beams to be installed along the tall supports.

20210220-dsc04504

Temporary structures have been dismantled on older sections of the canopy, which can be seen missing from the left side of the photo above.

20210220-dsc04507
20210220-dsc04506
20210213 DSC04229 8504998

Comparing today’s progress to the image above from last week, we can get a better idea of the progress of the seemingly simultaneous temporary support removal and addition.

20210220-dsc04509
20210220-dsc04510
20210220-dsc04511

We can see the various curves slowly taking shape as the canopy work progresses.

20210220-dsc04508

Here is another look at the peak the latest temporary supports create.

20210220-dsc04497

Not much has changed at the construction site as canopy beams remain stored there, waiting to be hoisted up to continue the canopy work on top of the peak.

20210220-img_20210220_091235
20210220-img_20210220_091220

TRON Lightcycle / Run is not expected to open in time for Walt Disney World’s 50th anniversary as the opening date has been delayed. However, we will continue to keep you updated with the latest information as construction progresses.

Can’t wait to see this attraction? You can watch our POV of TRON Lightcycle Power Run in Shanghai Disneyland below: